In Bromont, where ski slopes give way to water slides in the summer, a new attraction is about to take shape: the Tornado Wave, a spectacular water slide set to bring even more thrills to the mountain’s water park. Behind this upcoming wave of fun stands AGF’s well-rooted expertise, in partnership with Construction Longer.
A seasonal project with unique challenges
Adding this water slide goes far beyond just building a simple pool. It is a technical project divided into six phases, including the construction of a service and pumping building, as well as the installation of a complex rebar structure: footings, foundations, walls, structural slab, pile caps and columns. In total, 125 metric tonnes of steel were used to ensure the strength and durability of the infrastructure.
What makes this project particularly unique? Its mountain location. This setting demands precise management of workspaces, adapted handling and close coordination among all trades working on site.
Precision, consistency and expertise
Since May 8, 2025, the AGF Sherbrooke team, consisting of 2 to 4 specialized workers, has been progressing with efficiency. Even in this unconventional logistical environment, our team has demonstrated agility while maintaining the highest quality standards.
As the final stages approach, most of the work is now complete. Only a roof slab and a few foundations remain to be finished before water slide enthusiasts can enjoy this new summer installation.
A collaboration that flows naturally
This project also highlights the strong trust-based relationship between AGF and Construction Longer. Thanks to smooth communication and a shared understanding of on-site realities, this collaboration has been carried out with exemplary teamwork.
At AGF, every project is an opportunity to push boundaries, innovate and deliver with excellence. Even in the mountains, our foundations are solid and our passion runs deep.